The floor plans show the station now (top) and on completion. The new access to the walkway is on the right hand side as you come into the building, between the stairs to the car park and the booking office machines.
The need was amply demonstrated as I got off the train - helped a mother up the stairs with her pushchair. She can't wait for the work to be completed.
It looks as though the steelwork will arrive on site during July and work will continue across the summer with completion in September. There will be delays as some of the work depends on having the tracks beneath taken out of service. This has been one of the causes of delay so far, as the Chiltern Line has been a diversionary route for other lines and gaining possession hasn't been without problems.
Hopefully, things should pick up pace now.
Incidentally, in answer to a question earlier - the lifts are 16-person lifts with walk through access, so they are perfectly capable of taking a bike, should you wish to.
Also, two dates for the diary for residents immediately around the site. The heavy work of installing the foundations and the piledriving is all complete, but on the 17th and 26th of July, the steel sections are scheduled for installation and that will involve night work and a big crane. The noise will be nothing like that of the foundation work, but there will be some.