Warwick Road works
Part of the Warwick Road improvement programme includes work on the remainder of the road. Much of this is new lines on the road or changes to parking orders. At the junction of Broad Road and Warwick Road, we've built out on the junction and the give way lines will be repainted to improve sight lines down the hill into the Green.
There will also be a new pedestrian refuge just to the west of the Broad Rd junction, which caused some concern once I saw the markings on the road. Residents had also raised concerns that the island would force larger vehicles to swerve around it and there were doubts that some would be able to make the adjustment in the space allowed.
It was complicated by the bus stop on the other side of the road, which is used regularly by drivers to pause to catch up with their timetable before a crew changeover in the Green.
The design team came out on site and brought some traffic cones to create a temporary obstruction to mimic the changes in the road layout. We watched buses and trucks as they passed the site and as a result, the white road markings will be extended down towards St Mary's Close and slight adjustments made to the sizing of the refuge.
Monday, July 21, 2014
Road repairs - Cottesbrooke Road
As a result of an inspection, there are some localised repairs to be made to the road surface on Cottesbrooke Road.
The work is due to start during the week of the 28 July 2014 and is estimated to take about five days, with work being carried out between the hours of 8am and 6pm.
Road closures will be in place while work is in progress and there will be some restriction on access to property. Please don't park vehicles on this stretch of the road during this period, as they may have to be removed and there will be a charge for release. If you need urgent access to your property, then ask the crew on site or call 0121 303 6644 (option 2). Pedestrian access will be maintained throughout.
The work is due to start during the week of the 28 July 2014 and is estimated to take about five days, with work being carried out between the hours of 8am and 6pm.
Road closures will be in place while work is in progress and there will be some restriction on access to property. Please don't park vehicles on this stretch of the road during this period, as they may have to be removed and there will be a charge for release. If you need urgent access to your property, then ask the crew on site or call 0121 303 6644 (option 2). Pedestrian access will be maintained throughout.
Sunday, July 20, 2014
Acocks Green Station Update
Work continues on the lift installation at the station, with the start of work to build the bridge out from the existing building and the tower blockwork starting to go in.